How to commission and inspect the newly purchased dry shotcrete machine?

Date:2020-02-27     Label:

shotcrete machine

dry shotcrete machine

When a newly purchased dry shotcrete machine is put into use, will you conduct a routine inspection? Is your inspection in place? In order to avoid your worries, and to make it easy for you to use dry shotcrete machine, the following, please the professional technicians of China Coal to tell you what inspections should be done before starting:

1. Check whether the contacts of each line of the electric control system are firm and whether there is leakage.

2. Observe the oil window of the dry shotcrete machine and check whether the lubricating oil in the reducer is sufficient (the lubricating oil reaches half of the oil window is sufficient).

3. Check whether the parts of dry shotcrete machine are connected properly and firmly.

4. Dry shotcrete machine under short-term operation to grasp the rotation (note whether the running direction is consistent with the arrow, do not idle for a long time).

5. Check the pressing force exerted by the pressing mechanism on the rubber plate, first move the nut wrench on the rod of the pressing device, and initially tighten; then tighten it 2-3 times until the rubber plate does not leak air.

How to commission and inspect the newly purchased dry shotcrete machine?

+

+