In order to make the wet shotcrete machine start successfully in one time, it is the key to do the basic work well before starting. What basic work should be done? On this issue, the technical personnel are summarized as follows:
1. Check whether the power of wet shotcrete machine is normal.
2. Check the motor and gear oil pump, and make several turns.
3. Turn on the pressure gauge switch and release the pressure regulating handwheel of the relief valve.
4. Put the suction tube of the wet shotcrete machine into the clear water to test the machine.
5. Check whether the steering direction of the motor and gear oil pump is correct.
6. Check whether the hydraulic reversing valve block can control the reciprocating movement of the oil cylinder.
It seems troublesome to do the basic work before starting the wet shotcrete machine. It is of great significance to the normal start-up. I hope everyone pays great attention to it.